|
This chapter is primarily for senior managers, line managers,
and staff and their representatives.
 | People are the key asset. |
 | Staff must be properly supported in
carrying through efficiency programmes and competitions. |
 | Staff must be supported in dealing with the
personal implications of change. |
 | Depending on the circumstances, TUPE
protects staff when their work transfers to another employer. |
 | Health and safety responsibilities
continue. |
|
DEVELOPING AN EFFECTIVE HUMAN RESOURCE STRATEGY
Essential requirements
3.1 Poor handling of staff and ineffective or
irregular communication during efficiency exercises can affect staff attitudes and
motivation badly. As a result, the organisation's efficiency and effectiveness will be
reduced and staff's job satisfaction will be undermined. Indeed, this adverse effect is
likely to extend into areas outside the scope of the efficiency review.
3.2 Departments should have strategies for
addressing the human resource issues that are likely to arise before, during and after
efficiency reviews. Officers should be appointed to oversee implementation of these
strategies reporting to senior managers who have overall responsibility.
3.3 Strategies should ensure that:
 | full staff involvement in the process is encouraged wherever possible; |
 | staff affected by change are provided with appropriate advice and assistance at key
stages to enable them to make informed decisions on their future options; |
 | there is the fullest possible consultation and, as appropriate, negotiation with
recognised trade unions, or, if none, other independent staff representatives; |
 | (in order to be prudent), TUPE is assumed to apply, until the position is clearly
established one way or the other (21), so that, at
the appropriate time, staff are provided with: advice on the implications of transferring
to external providers on their current terms and conditions and also on broadly comparable
pensions; (22,23) professional
counselling; and are
given opportunities to make contact with potential providers; |
 | statutory consultation required under TUPE is "planned in" and properly
managed. Departmental legal advisers and personnel staff need to be involved. |
 | steps are taken to ensure that change is as smooth as possible, by producing a
transition or transfer plan which sets out responsibilities and key objectives. The
involvement of the private sector contractor should be secured in this plan in order to
maximise the chances of success. |
 | managers carry out the efficiency exercise without delay, to maximise certainty and
minimise uncertainty, and achieve the quickest and best possible result; and |
 | effective communications are maintained. |
Effective communications
3.4 Poor or irregular communication can increase
the uncertainties associated with efficiency reviews and erode trust between staff, their
managers and colleagues. Departments should have a communications strategy to ensure that
staff are kept informed about progress of efficiency reviews. A senior officer should be
responsible for communication. The timing and amount of information needs
judgement,
depending on the audience and the stage of the efficiency programme. But regular
communication, even when there is little news to report, can help build trust and
discourage rumours.
3.5 In market tests, the requirement for there to
be proper separation between clients and in-house bid teams, so-called "Chinese
Walls", can accentuate communication difficulties. Departments should ensure that
such barriers are reasonable and in keeping with proprieties associated with tendering,
but that Chinese Walls do not prevent staff concerns being addressed. The need for Chinese
Walls should be addressed in devising a communications strategy.
Preference exercises, when competition is the
option
3.6 At an early stage in planning,
Departments should consider whether there is scope for offering staff, in areas being
subjected to competitive tendering, choices on whether to transfer to any successful
external bidder or be redeployed to another job within the Civil Service. Such preference
exercises need to be justified on a case by case basis, taking into account the potential
benefits and disbenefits, in particular, whether:
 | there is really scope to offer redeployment to staff and, if there are vacancies
available, whether the skills and experience of the staff concerned would be suitable; |
 | staff will have enough information at the time the preference exercise is offered to
make informed choices; |
 | given the nature of the market, contractors would be likely to be able to maintain
continuity of service with a significantly reduced number of staff transferring; |
 | clarity has been achieved on the application of TUPE (see paragraph
3.14), which would remove the scope for redeployments. |
Non-discrimination
3.7 The Government and the Civil Service (as an
employer) are committed to a policy of equality of opportunity. Departments should ensure
that, in this context, equal opportunities policies are upheld throughout competitive
process and care should be taken to ensure that the impact of efficiency reviews
has regard to equal opportunities considerations. Efficiency reviews can adversely affect
equal opportunities if they mostly cover services or activities in which particular groups
are over represented (for example, women and ethnic minorities tend to be over represented
in clerical work). Therefore, efficiency exercises should not always concentrate on these
areas, but the search for efficiency should cover all parts of a Department. When
running competitions, Departments must observe the following.
 | Specifying requirements in competitions equal opportunities cannot be used
as selection or award criteria. However, particular requirements can feature as contract
conditions, when they are relevant to the contract, are justified by the service
specification provided, and they are compatible with EC Treaty obligations (for example,
to ensure there is no discrimination against suppliers or workers from other Member
States). |
 | Bidding however, tenderers can be asked to indicate whether, when drawing
up their bids, they have taken account of those legal obligations which are in force in
the place where the service is carried out. These obligations would include: the principle
of equal treatment for men, women, all ethnic groups; and duties under the Disability
Discrimination Act 1995 toward employees, the public and customers. |
 | Market testing in-house bids must comply with Departmental equal
opportunities programmes and commitments. |
 | Evaluation see above, Bidding. |
 | Contracts see above, Specifying requirements in competitions. |
Employees with disabilities
3.8 Departments have obligations under the
Disability Discrimination Act 1995 toward disabled employees and should consider these
when undertaking efficiency reviews and competitions. Specific instances where action will
be necessary are as follows:
 | Where there is a likelihood of employees with disabilities who require special aids or
specially tailored job specifications transferring to the private sector, Departments will
need to consider whether those needs will be met by a potentially successful service
provider, particularly where the employee threshold might be below that required by the
Disability Discrimination Act. |
 | Where aids and adaptations have been provided by the Employment Service, or its
predecessors, the equipment is personal to the user and should transfer with them. |
 | To facilitate a smooth transfer of disabled staff to private sector providers,
Departments should bring to providers' attention legislation on disabled persons and the
advice and funding available to them. |
Redundancies
3.9 In some cases, where work is to be carried out
by the private sector, there will need to be redeployment of staff currently carrying out
the work, voluntary early retirements and, in some cases, redundancies. However,
Departments have no liability for redundancy in the case of staff who:
 | are redeployed in the Civil Service. |
 | are transferred under TUPE (see paragraph 3.13, below) |
 | refuse to transfer under TUPE and are therefore deemed to have resigned and not to have
been dismissed. |
 | (where TUPE does not apply) resign to take up employment offered by the new employer. |
3.10 In circumstances where TUPE does not apply,
any redundancies resulting from transferring services to the private sector should be
dealt with under the provisions of the relevant redundancy agreement. Most civil servants
are entitled to compensation if they are dismissed or retired on grounds of redundancy.
The costs of compensation will fall on Departmental votes and will need to be taken into
account in evaluation.
3.11 Compensation terms for civil servants made
redundant are set out in the Civil Service Compensation Scheme (CSCS), and guidance on
terms is contained in the PCSPS Pensions Manual (Volume 4). The benefits payable on early
departure are outlined in the PCSPS booklet Early Retirement and Redundancy. Where
redundancies are being contemplated or where TUPE applies, or might apply, Departments
should obtain estimates of redundancy costs.
TRANSFER OF UNDERTAKINGS (PROTECTION OF EMPLOYMENT)
REGULATIONS TUPE
Introduction
3.12 The Transfer of Undertakings (Protection of
Employment) Regulations 1981 (as amended), known as "TUPE", implement the 1977
European Council Directive 77/187/EEC, which is generally known as the Acquired Rights
Directive (ARD) (24). References to "TUPE"
include the Directive.
Provisions
3.13 In broad terms, TUPE protects employees' terms
and conditions (except in relation to future occupational pensions see paragraph 3.26 below) when the business in which they work is transferred
from one employer to another, and the business retains its identity. When TUPE applies,
employment with the new (or transferee) employer is treated as continuous from the date of
the employee's start with the first (or transferor) employer. Terms and conditions cannot
be changed where the operative reason for the change is the transfer of the undertaking,
although changes for other reasons may be negotiated. It is the responsibility of
Departments, as employers: to satisfy themselves, on the basis of advice from the
Department's legal advisers, whether TUPE applies in particular circumstances; to ensure
that TUPE is honoured, where it does apply (including the consultative requirements) up to
the time of transfer; and to ensure that contractors accept their responsibilities when
TUPE applies.
Assessing whether TUPE will apply
3.14 Whether TUPE applies depends on all the
relevant facts of the case. Legal advice should always be taken and lawyers fully
appraised of all relevant facts. The case law of the European Court of Justice
(ECJ)
suggests that TUPE is likely to apply to a contract for services awarded to the private
sector (including companies formed as a result of management or employee buyouts)
following competitive tendering, if an economic entity has been transferred and remains in
existence performing the same or similar activities. Departments may specify (see Chapter
5) that staff are to transfer (which will cause TUPE to operate), or else must give a view
on the likely application of TUPE. Departments must not rely on contractors' assertions or
on the legal advice which contractors themselves may have taken, but must seek the advice
of their own legal advisers. The ECJ has identified a number of factors to be taken into
account (although not all necessarily have to be present) in determining whether a
business has been transferred as a going concern and thus attracts TUPE's protection:
 | the type of undertaking or business in question; |
 | whether or not the tangible assets of the business (whether fixed or moveable) or the
entitlement to use such assets (even if ownership is not transferred) have been
transferred; |
 | the value of its intangible assets at the time of the transfer; |
 | whether the majority of the transferor undertaking's employees are taken over by the
transferee employer; |
 | whether the customers of the former business are transferred; |
 | the degree of similarity between the activities carried on before and after the
transfer; |
 | the period, if any, for which activities were suspended. |
3.15 TUPE does not apply when:
 | the assets of a business are simply disposed of without its operation being continued by
the new owner; |
 | work remains in-house or is undertaken by another Government Department; |
 | a contract ends and is assigned to a new employer and insufficient of the factors in
paragraph 3.14 are present. Whether factors are insufficient or not will depend on the
circumstances of each case; |
 | neither significant assets nor a significant proportion of staff in terms of numbers or
skills, are transferred. |
In cases where it is unclear whether TUPE will apply, Departments should deal with
releasing information and consultation as if TUPE does apply. Departments should give
potential bidders the choice of producing proposals on the basis of either or both
possibilities. The reasons for their views on the applicability of TUPE should also be
sought as part of the tendering process, with the Department reserving the right not to
accept a bid that it does not agree with. As soon as it becomes clear whether or not TUPE
applies, staff and recognised trade unions, or, if none, other independent staff
representatives, should be told. When dealing with requests for supplementary information
(see Chapter 5), Departments should not provide the information
that would be required under TUPE to a potential bidder who has said that it is not going
to submit a TUPE-based bid.
Effect of TUPE applying
3.16 If TUPE applies, the transferee employer:
 | Takes over the contracts of employment of all the employees who were employed in
the undertaking at the time of the transfer, (unless there are dismissals for economic,
technical or organisational ("ETO") reasons, entailing changes in the workforce
see paragraph 3.36), on the same terms and conditions as
they were employed by the transferor, except in relation to future occupational pensions
entitlement (see paragraphs 3.26 and 3.27). |
 | Takes over all rights, powers, duties and liabilities in respect of the transferring
employees. |
 | Takes over any collective agreement, including recognition agreements, applicable to the
employees transferring. |
 | Is obliged to make information available to workers' representatives and the transferor
employer, and to consult workers' representatives on matters relating to the transfer. |
3.17 If TUPE does not apply, then a
contractor is under no obligation to employ any of those currently providing the services
being contracted out. If contractors want to offer employment, this would be on the basis
of inviting individuals to enter into entirely new contracts of employment. In these
circumstances, requirements relating to terms and conditions of service should not be
imposed on contractors, except where there are reasons for doing so related to the
performance of the service in question. However, as one of the "tests" for TUPE
relates to staff being taken on, the act of taking on some (or all) staff may trigger a
TUPE transfer.
Transfers, redeployments and secondments
Transfers
3.18 If TUPE applies all those working in the
undertaking or that part of it transferred will be transferred, except any dismissed for
ETO reasons (see paragraph 3.36). Employees have the right to
object to the transfer of their employment, but unless the transferor employer is willing
to redeploy them away from the part of the undertaking being transferred, they will be
treated as having resigned rather than being dismissed by the transferor. Such a
resignation does not entitle an employee to redundancy payments or to claim unfair
dismissal.
3.19 Employees have the right to resign and claim
constructive unfair dismissal if their working conditions are significantly changed
without their consent and to their detriment. Resignation because of a change to the
identity of their employer will not entitle them to claim unfair dismissal unless the
change is significant and to their detriment.
Redeployments before transfers
3.20 At an early stage, there may be scope
for Departments to redeploy (25) staff not crucial to
the performance of the contract (see paragraph 3.6), provided
that this is acceptable to the Department and the staff concerned and, to the
transferee contractor (if known). Also, it should not of itself give rise to causally
related redundancies. In any consultations with the contractor about who might be
redeployed prior to the date of transfer, Departments should take account of Civil Service
policies on equal opportunities (26).
Secondments
3.21 In some circumstances, it may be possible for
Departments to second one or more of the staff currently employed on the work to the
transferee employer rather than them transferring under TUPE. Secondments must be genuine
and the consent of all those involved will be needed. Departments should only offer
secondments if they will be able to re-absorb secondees at the end of the secondment
period.
Terms and conditions
3.22 Terms and conditions of employment of
transferred employees may be amended by agreement between the new employer and the
employees (or possibly their representatives), provided the transfer is not the operative
reason for the change. However, any change without consent would normally be void and
unenforceable and provide grounds for a claim for constructive unfair dismissal on grounds
of breach of contract.
3.23 Some terms and conditions will have no meaning
outside the Civil Service. For example, the restrictions on the political activities of
civil servants cannot be justified in private employment. Others would be difficult to
replicate: for example, the right of appeal to the Civil Service Appeal Board against
dismissal, although many large organisations have formal appeals procedures to which
transferred staff should have access. Transferee employers and staff (and their
representatives) should reach early agreement on such matters, without disturbing the
principal terms and conditions.
Staff on individual terms and conditions
3.24 Some civil servants have individual terms and
conditions of employment, for example, part-time or flexible working. These transfer in
respect of the employees concerned.
Staff on career breaks
3.25 The position of staff on career breaks needs
careful consideration. Whether or not they remain employed by their Department during the
break will depend on the terms of the career break agreement. If they remain employed and
the unit to which they would normally have returned is transferred under TUPE, the
Department should consider whether they form part of the transfer or whether redeployment
would be possible in the circumstances and preferable to the person concerned and the
Department.
Occupational pensions
Pensions in the new employment (27)
3.26 Future occupational pension arrangements are
not covered by the Acquired Rights Directive and therefore are not transferred by
TUPE,
but they are protected by UK law. Employment contracts cannot normally be changed
unilaterally. This would be the effect of ending contractual entitlement to future
occupational pension provision when work transfers and would give rise to a risk of a
successful claim for constructive unfair dismissal. To guard against this risk, the
Government requires that, when staff transfer from Crown employment with TUPE protection,
broadly comparable occupational pension provision for future service must be secured for
them from their new employer. Where broadly comparable pensions are not, or cannot be,
provided, employees should be suitably compensated.
3.27 Bidders should therefore be asked, if
submitting bids to which TUPE would apply, to state in their tenders the occupational
pension benefits to which employees will be entitled after transfer, or any compensation
for less generous pension provision for example, higher salaries, part of which is
paid into a private insurance pension scheme, or employee share ownership plan.
3.28 The Government Actuary's Department (GAD)
should be asked to certify whether pension arrangements offered for future service with
the new employer are likely to provide broadly comparable benefits to the Principal Civil
Service Pension Scheme (PCSPS) based on actuarial assessment, and if not, the extent of
any detriment, taking into account any compensating changes to other terms and conditions.
The cost of any detriment payments should be taken into account when bids are evaluated.
Only defined benefit schemes will be certified as being broadly comparable to the
PCSPS.
Existing pension entitlement
3.29 Occupational pension entitlement which is
accrued at the time of transfer is protected by Social Security legislation, in the same
way and to the same extent as for civil servants leaving the PCSPS voluntarily. Civil
servants transferring under TUPE will always have the same options as those who leave the
PCSPS voluntarily. They may preserve their accrued pension (provided they have two or more
years' qualifying service) in the PCSPS for payment at age 60. They may transfer an amount
equivalent in value to these preserved benefits to the new employer's pension scheme,
provided that scheme agrees, or to another pension arrangement, for example a personal
pension. Benefits preserved in the PCSPS are revalued each year in line with movements in
the Retail Price Index. However, no account will be taken of future salary movements for
the individual in question, or of earnings increases in general. Care should therefore be
taken not to imply to transferring staff that benefits preserved in the PCSPS would
ultimately have the same value as the benefits they would have received in respect of
service to the date of transfer of employment had they remained in the PCSPS.
Bulk transfers
3.30 Where staff are transferred compulsorily from
the Civil Service, it may be possible to organise the option of a bulk transfer value
payment to the new employer. This is intended to enable staff to be offered more
attractive terms for transferring their PCSPS benefits to their new employer's pension
scheme than would be available with an individual transfer, and to reflect the special
circumstances of such a transfer of employment. A bulk transfer arrangement would give
transferring staff the option of preserving the linkage to their future salary of benefits
which derive from their service with the PCSPS. If a bulk transfer arrangement is
available, it will for the individual PCSPS member concerned to decide whether to take
advantage of it. Departments must not give advice to individuals on their choice.
General information may be distributed, but only after professional advice has been taken.
3.31 Employing departments should ask GAD, as
scheme actuary to the PCSPS, to enter into discussions with bidders with the aim of
agreeing bulk transfer arrangements for transferring staff that offer credits in the new
employer's pension scheme that are of similar value to the benefits they would have
received in respect of service to the date of transfer had they remained in the
PCSPS.
3.32 The availability of bulk transfers depends on
whether a satisfactory agreement is concluded on the benefits to be provided and the
amount of the transfer payment with the actuary to the new employer's pension scheme.
Departments must involve GAD as soon as a compulsory transfer of employment affecting
civil servants seems likely and before a contract has been let. Guidance on the pension
actions required by departments in cases of bulk transfers is contained in the PCSPS
Pensions Manual, Volume 8, section 9. GAD must be involved early to give time for
negotiations before bid evaluation. If negotiation of bulk transfers is left too late, or
indications are given of the preferred bidder before negotiations can be concluded, it can
make a satisfactory outcome much harder for GAD to achieve. The fact that a bidder has not
been prepared to agree a bulk transfer on terms which give value for money to the taxpayer
should be considered a significant disadvantage of that bid.
3.33 The amount of transfer value payment is
recommended by GAD and is authorised by the Cabinet Office, Office of Public Service (28). Payments reflect the value of liabilities previously
borne by the PCSPS (the methodology underlying bulk transfer payments is well established
and fair, both to the transferee and the taxpayer). Under no circumstances will bulk
transfer payments be available to money purchase pension arrangements because money
purchase schemes cannot be assessed as comparable with final salary schemes.
Ongoing liabilities
3.34 Departments should not incur liabilities in
respect of pension entitlements of transferred civil servants in their new employment over
which they will have no control following transfer. The responsibility for pension
matters, as for other terms and conditions of employment, will rest with the new employer
after transfer. Departments should not make any specific commitments to employees about
individual elements of their pension arrangements in the new employment.
Staff outside the PCSPS
3.35 Staff in non-departmental public bodies may
have different pension arrangements. These may take the form of schemes which are
"by-analogy" to the PCSPS or there may be a free-standing pension scheme with
its own rules. The same considerations apply to staff of these bodies as for members of
the PCSPS, both in respect of pension rights that accrue after a transfer of employment
and the possibility of a transfer of existing entitlements. Special considerations may
apply where pension schemes are backed by a fund with real assets. The sponsor department
should obtain legal and actuarial advice on the pensions implications for these staff and
the likely financial consequences of offering transfer values.
Dismissals connected with transfers and redundancies
Unfair dismissals
3.36 TUPE provides that dismissals connected
with a transfer will automatically be unfair unless they are for economic, technical or
organisational reasons involving changes in the workforce, which may include (although it
will depend on the facts in each case):
Economic where demand for an employer's output falls to such an extent
that the business cannot continue trading unless staff are dismissed.
Technical an employer wishes to use new technology and transferred
employees do not have the necessary skills.
Organisational a new employer operates at a different location from the
previous employer and it is not practical to relocate transferred staff.
3.37 However, the greater the time lapse between a
transfer and dismissal, the less likely it is that they will be viewed as being connected.
Timing of redundancies
3.38 Staff involved in providing services that are
to be contracted out under TUPE should not be made redundant immediately before or after
transfers. It would be difficult in these circumstances for Departments (or contractors)
to justify such redundancies on economic, technical or organisational grounds. The
liability for any unfair dismissal compensation awarded to staff after the transfer would
rest with the contractor concerned.
Compensation for redundancy
3.39 Proper redundancy procedures should be
followed to avoid dismissals being designated unfair on procedural grounds. The provisions
relating to compensation for civil servants who are made redundant are contained in the
CSCS.
3.40 Compensation for redundancy after transfer to
the new employer will be payable by the new employer on the basis of the aggregate length
of service within the Civil Service of the transferee employer. The payment should be
calculated on terms which are near identical as possible to the CSCS terms, although, in
some cases, under Inland Revenue rules, such compensation cannot be paid from an approved
retirement benefits scheme.
3.41 Further detailed guidance about redundancy
benefits under the CSCS is available from the Cabinet Office, Office of Public Service.
Guidance on the form of redundancy benefits proposed by bidders is available from GAD.
Indemnities
3.42 Value for money is best achieved by a
"clean break" when staff transfer to the private sector. It is not the
Government's policy, therefore, to give indemnities against the possibility of
redundancies arising after a TUPE transfer, unless provided for in statute, or agreed in
exceptional circumstances between Departments and their Treasury Spending Teams. The
criteria for such exceptions, which were issued by the Treasury in 1994 (29), address any need there might be to reassure staff that
their redundancy entitlements would be honoured by a new employer.
In summary, the criteria are:
 | the importance of maintaining staff morale and goodwill; |
 | whether or not a sharp rundown in business is likely after the transfer; |
 | the extent to which the business is underpinned by Government contracts and the length
of such contracts; |
 | the degree of competition, actual or potential, in the market; |
 | the extent to which bidders have unencumbered capital assets which might be used to
finance redundancy compensation; |
 | the likely financial standing of bidders. |
3.43 If a guarantee or indemnity is agreed, it
should:
 | be called on only if the contractor goes into liquidation and cannot meet his redundancy
liabilities; |
 | be limited to historic rights (indexed to the Retail Price Index); |
 | be limited in time; |
 | be designed so as to minimise the cost to the Exchequer in the event of the indemnity or
guarantee being called. |
3.44 The presumption against providing redundancy
guarantees also extends to redundancy cost sharing schemes. However, in the case of
privatisations where redundancy costs are foreseen, Departments might consider entering
into a commitment to meet a share of the costs as part of the sale agreement. To ensure a
level playing field, any such agreements should not be used to show favour to any
particular bidder. Care should also be taken not to create an incentive for the new
employer to make staff redundant during the period when the cost-sharing arrangement is in
force.
3.45 Indemnities must never be given against the
possibility of amendment to the Acquired Rights Directive and TUPE, as Governments do not
give undertakings which might tie their hands about future changes in legislation.
ANTICIPATING RETENDERING
3.46 If a contract has been awarded in
circumstances in which TUPE applies, there is no certainty that it would apply again if on
retendering the contract were to be awarded to another supplier. It would depend on the
circumstances (see paragraph 3.14, above). When it becomes
clear that the services will be retendered (Chapter 9)
Departments should consider with the incumbent contractor (without compromising the
competition when it takes place) whether to specify that staff should transfer to any new
contractor. This would cause TUPE to operate. However in awarding the first contract, it
would be prudent to anticipate that TUPE would be likely to apply and to ensure that
contracts:
 | entitle the Department to information about the contractor's staff that can be passed
onto other tenderers; |
 | commit the contractor to facilitate the transfer to any new contractor at the end of the
contract, in particular by providing information on staff. |
Without this, Departments may find it difficult to attract alternative contractors at
the end of the contract period.
RELEASING INFORMATION ABOUT STAFF
3.47 Departments should give potential bidders full
and accurate information to allow them to calculate potential liabilities under
TUPE. In
cases where external bidders are successful, then the material elements of staff records
need to be transferred to the new employer (see below). In each case, Departments must
take legal advice to satisfy themselves that they are fulfilling their obligations under
the common law principle of confidentiality and the Data Protection Act (if relevant).
 | The common law principle of
confidentiality represents a ban on disclosure of information given in
confidence. This means that it is important to appreciate the circumstances and
understandings in effect when the information was collected (normally at recruitment). |
 | The Data Protection Act 1994
incorporates the principle of confidentiality to a large extent by requiring that
information be obtained and processed lawfully. It also requires that information is
obtained and processed fairly. Employees should not have been misled at the time the
information was gathered as to the uses to which information they provide will be put. The
Act also requires that the purposes information is to be used for should be registered
with the Data Protection Registrar. |
|
What to consider
3.48 In considering their obligations when TUPE
applies, Departments should bear in mind that:
 | there is no general prescription that can be given as to what can and cannot be
disclosed it will depend on the circumstances of the case; |
 | there is no question of breach of the law if employees agree to disclosure of
information held about them; |
 | consent to disclosure will not normally be required, although care would be needed if
commitments not to disclose had been given to employees; |
 | it will be good practice to ensure employees are aware of disclosure and the contents
beforehand, even when disclosure is only anticipated; |
 | appropriate registrations under the Data Protection Act should include a provision for
disclosure to "employers past, current or prospective". |
Transferring confidential information
3.49 Confidential information, for instance, on
security vetting, discipline, exchanges about the status of grades who are not politically
free should not, in any circumstances, go to the new organisation. Live
disciplinary cases should be brought to a head and settled before transfer.
3.50 Where it is proposed to provide copies of
staff reports on non-industrial employees, the staff concerned must be informed and given
an opportunity to object. In all cases, the original reports should remain with the
Departments concerned.
Providing information if TUPE does not apply
3.51 If TUPE does not apply there is no
automatic transfer of staff and if the new service provider recruits among existing staff,
only references should be provided (if requested) and not annual reports. However,
where the new employer is a statutory body, or a controlled "fringe body",
likely to follow closely Civil Service terms and conditions, the two most recent annual
reports should be transferred, provided that the individuals do not object. In cases of
doubt, the aim should be to resolve the general position in agreement with the new
employer and staff representatives. Departments may consider it appropriate, in some
cases, to offer individual references on each member of staff rather than transfer annual
reports.
KEEPING STAFF INFORMED ABOUT TUPE
3.52 From the outset, Departments must ensure that
staff are informed about the possibility of TUPE applying and the likely implications.
Staff must be reassured that appropriate steps will be taken to ensure that, in the event
of them transferring to a contractor, their terms and conditions will be safeguarded.
Failure to address their concerns will have an adverse effect on morale and, in extreme
cases, the competition and the whole efficiency programme.
3.53 Once it has been decided that TUPE will apply,
staff and their representatives (usually recognised trade unions) should be informed. If
staff are to be transferred, they should be properly briefed and have the opportunity to
discuss the implications, preferably, with the new employer.
TRADE UNION CONSULTATION
Statutory provisions
3.54 Departments' statutory obligations include:
 | notifying trade unions, where they are recognised, or independent representatives of
employees in other cases, of areas that are to be subjected to efficiency reviews, but not
negotiations on whether any particular activity should be subjected to review; |
 | giving them copies of advertisements in the Official Journal of the European
Communities; |
 | providing them with a copy of strategies to be used in tendering projects and the
opportunity to comment on them. |
3.55 In addition, in market tests, managers in
charge of in-house bid teams must consult recognised trade unions or, if there are
none, independent staff representatives at local level. This will be particularly
important where in-house teams are proposing any variations to working practices (see Chapter 6).
Consultations about the application of TUPE
3.56 When TUPE applies, the transferor and
transferee employer must inform and consult either the independent trade unions recognised
in respect of transferring employees who may be affected by the transfer or by measures
taken in connection with it, or, if none, other independent elected staff representatives,
about the transfer. If measures are envisaged in relation to any employees in connection
with a transfer, their employer must consult the unions or staff representatives about the
measures that will be taken. Consultation should be conducted with a view to seeking
agreement. If unable to agree, the Department must give reasons.
3.57 Long enough before a transfer for meaningful
consultation to take place, the following information should be provided about transfer
arrangements:
 | notification that transfers may take place and confirmation when it is clear
whether TUPE will apply, with reasons and details of timings; |
 | the legal, economic and social implications of transfers of the affected employees; |
 | whether employers intend to take measures which will affect employees and, if so, what.
Employees should be told if no measures are envisaged. |
Collective bargaining versus consultation
3.58 Departments should distinguish between
collective bargaining and consultation and ensure that their relationships with recognised
trade unions or other independent staff representatives are clear in respect of each.
Where a union is recognised for collective bargaining on a matter, it has a statutory
right to receive certain information on request. In the case of consultation, however,
management has discretion on how much information to make available in the circumstances,
in order to achieve effective consultation.
3.59 There is also a distinction between
recognition in relation to terms and conditions of service and recognition in relation to
decisions which will in turn affect terms and conditions. Recognition in respect of terms
and conditions does not automatically mean that there is recognition in respect of
management decisions which may lead to effects on terms and conditions.
3.60 Departments should consult recognised trade
unions, or, if none, other independent staff representatives on decisions about efficiency
programmes and competition, but they do not need to recognise them on such matters. They
should be careful not to confuse this sort of consultation with negotiations which can
follow from recognition.
3.61 Departments should satisfy themselves that
their recognition arrangements will not expose them to the risks of delaying
implementation of their efficiency exercises and competitions.
HEALTH AND SAFETY
Responsibilities
3.62 When Departments are considering engaging
contractors to work on their premises, they must consider the health and safety
implications. The Health and Safety at Work etc Act 1974 (the HSW Act) requires every
employer to conduct his or her activities in such a way that people not in their
employment, but who nevertheless may be affected by their activities are, so far as is
reasonably practicable, not exposed to any risk to their health or safety. Employers have
a duty to ascertain if the operations of contractors on their premises are likely to give
rise to any hazards which could affect their own employees, contractors and their
employees, other people on site or members of the public.
Advice
3.63 In the first instance, the person with
responsibility for health and safety in the Department should be consulted. Further
information is available from the Health and Safety Executive (Infoline: 0541 545500).
KEY MESSAGES
 | Staff are Departments' key assets and they
need to be trained for and supported through efficiency exercises. |
 | Effective and regular communication is
essential without it efficiency and effectiveness will be eroded, trust will be
undermined, and rumours will start. |
 | Equal opportunities should be honoured in
planning and carrying out efficiency programmes. |
 | TUPE protects staff terms and conditions,
when it applies, which depends on all the circumstances of the case legal advice
should always be taken. |
 | Broadly comparable occupational pension
provision should be offered by any new employer for future service, to avoid the risk of a
successful claim of unfair dismissal against the Crown. |
 | Past service rights in the PCSPS may be
preserved on the basis of early leaver benefits or transferred to another pension
arrangement willing to accept them, including that of the new employer's pension scheme,
in accordance with statutory provision for cash equivalent transfer values. Best
endeavours will be made to try to secure pension benefits for past service in the new
employer's pension scheme on a basis which will allow them to continue to be related to
future earnings. |
 | Information on staff should be provided,
depending on the circumstances, to bidders and new employers, for future service, subject
to respecting confidentiality, staff views and the Data Protection Act. |
 | Past service rights in the PCSPS will be
preserved, at least on the basis of early leaver benefits, and best endeavours will be
made to try and secure pension benefits for past service on a basis which will allow them
to continue to be related to future earnings. |
 | Recognised trade unions, or other
independent staff representatives, should be kept informed and consulted about efficiency
exercises (but not on whether any particular activity should be subject to review) and on
the implications for staff, whether TUPE applies or not. |
 | Departmental health and safety officers
should be consulted. |
|
SOURCES OF FURTHER
INFORMATION
 | The Transfer of Undertakings (Protection
of Employment) Regulations 1981, as amended. |
 | For Your Future Security Your
Pension Scheme Benefits Explained, 1996, published by the Civil Service Pensions
Division, Cabinet Office, Office of Public Service. |
 | OPS Pay Delegation Guidance Note 32:
Trade Union Recognition and Bargaining Arrangements, September 1994, amendment,
November 1995. |
 | Guidance on Privatisations and
Redundancy Guarantees: letter from HM Treasury to Principal Establishment and Finance
Officers, 2 March 1994. |
 | Health and Safety Executive's Infoline:
tel 0541 545500. |
|
4. PREPARING THE GROUND SCOPING AND ASSESSING
FEASIBILITY
This chapter is primarily for project managers and senior
managers.
 | Refining in more detail the scope of the
service required and the competition or other option chosen in the
appraisal. |
 | Responsibilities of providers and clients
are separate but complementary and need to be identified. |
 | Risk should be identified. |
 | When all this is done, the feasibility of
the resulting efficiency programme should be tested. |
|
THE SCOPE FOR COMPETITION
Defining the scope (30)
4.1 Scoping involves determining how much of a
particular function or activity is to be included in a prospective competitive tender. It
might also be used to determine the scope for combining the competition with others,
including any PFI deal, or whether there are opportunities for selling services into wider
markets (31). It is important to take a long-term
view so as not to blight the future potential for maximising value for money or jeopardise
continuity of provision. Factors to be considered include:
 | The size of competitive tendering projects savings generally tend to vary
with the size of projects; projects covering activities with high pre-test costs are more
likely to offer greater savings in percentage terms than small ones; and the cost of
implementing small projects is likely to be higher than larger ones. Thus Departments
should be sure that the benefits are worth the process costs in the case of competitions
for activities with low pre-test costs. For these, they should look for opportunities to
link low value activities together or with higher value activities, in order to maximise
the potential savings from competition and minimise the process costs (see Chapter 2). |
 | Organisational boundaries having relatively small contracts restricted to
existing organisational boundaries can limit possibilities for restructuring in the
future. Departments should therefore take as broad a view as possible when identifying the
scope for projects rather than be restricted by current organisational boundaries, or
boundaries between Departments (see Chapter 1). |
 | Business processes Competitively tendering whole services or whole
business processes rather than individual functions can allow outcomes and outputs to be
specified more clearly, require fewer contract management interfaces and may facilitate
the better utilisation of any spare capacity, for example, by selling services into wider
markets. Future options for improving service provision are less likely to be constrained
when a holistic approach is taken. Departments should, where possible, avoid piecemeal
implementation where this would impact on process and contract management costs. |
Packaging (32)
4.2 Packaging or combining groups of related
processes together can promote competition especially where activities are too small to
make competition worthwhile on their own. Departments should package activities so as to
promote competition, considering the factors that can affect this, for instance:
 | Size larger packages (provided that they are not so big as to limit
competition) generate more private sector interest than small ones and can offer greater
scope for innovation. Also, smaller packages generally incur higher contract management
costs overall because of the greater number of contracts. However, Departments must take
care not to discriminate against smaller companies. |
 | Type of activity packaging totally unrelated activities together can deter
private sector interest. However, packaging capital projects with associated services may
have the opposite effect. |
 | Connections competitions can be compromised if activities are too closely
connected with other activities outside the competition. |
 | Market competencies grouping activities together so as to reflect existing
market competencies can assist in generating competition. However, the lack of an existing
market should not necessarily be taken as an indicator of limited private sector interest
as there might still be scope for the private sector to gear up in time. |
4.3 It may be appropriate for Departments to seek
informal advice from trade associations or contractors or staff representatives about the
relative attractiveness of different ways of packaging services. However, in doing so,
they must not discriminate in favour of particular suppliers.
Responsibilities of those involved with service provision
4.4 Responsibilities of service providers
usually include:
 | maintaining levels of service within a contract or Service Level Agreement at agreed
costs; |
 | managing service provision; |
 | liaising with the client over any changes in requirements. |
4.5 Clients' that is, Departments'
responsibilities usually include:
managing the budget allocated for the activity;
monitoring service provision within agreed standards;
agreeing changes to requirements with providers;
acting as the link between customers/end users and the suppliers on contractual matters;
monitoring the market place, with a view to retendering when the contract terms ends
(see Chapter 9);
considering future requirements and developing policy.
Risk
4.6 Risks need to be identified, evaluated, costed,
negotiated and managed. In any type of Public Private Partnership, risk should be
allocated to whoever can manage it at least cost (33).
Being able to secure risk transfer on worthwhile terms means ensuring the scope of the
contract is sufficiently widely drawn and that there is a shared understanding of what the
risks (and potential rewards) are. Depending on the service, the risks might include:
 | design and implementation risk to cost and time; |
 | operating and maintenance risks; |
 | demand or usage risks; |
 | staffing risks; |
 | quality risks meeting performance standards; |
 | cost risks which could impact on price; |
 | residual value risk; |
 | technology and obsolescence risk; |
 | regulation and similar risks. |
Whoever has risks placed with them needs to anticipate and manage the risks so that
better quality services at optimal cost are achieved.
Procurement strategies
4.7 The procurement strategy should be that most
likely to achieve better quality services at optimal costs. The strategy should cover:
style, timing, objectives (which should be related to the service specification) and the
resources available for the efficiency exercise, or competition;
the procurement procedure to follow under EC Procurement Rules;
the intended relationship between the Department and the service provider/contractor.
Style, timing, objectives, resources
4.8 In selecting an appropriate procurement
strategy, consultation with the private sector and staff may yield useful advice.
Departments should explore the relative risks and benefits associated with procurement,
carefully taking the following aspects into account:
the strategic importance of activities within the organisation;
the ease with which outcomes and outputs can be specified;
the cost of provision and size of the package being submitted to competition;
likely future requirements and the scope for utilising spare capacity;
the relationship with overall plans and strategies so as not to constrain future
potential or conflict with other initiatives;
resources available for implementation against those that each strategy will require;
the likely level of private sector interest, market development and capabilities;
the risks involved in delivering the service and the potential for transferring these to
the supplier.
EC Procurement Rules (34)
4.9 Unless the value of the services is less than
the relevant threshold, (exclusive of VAT), or there are other grounds of exclusion, the
EC Procurement Rules will apply. In relation to the procurement of services, the EC
Procurement Rules are implemented in the UK by the Public Services Contracts Regulations.
These rules normally require competition and lay down procedures, which include the
advertising of contracts in the Official Journal of the European Communities (OJEC), the
use of technical specifications, the selection of tenderers, and the award of the
contract. They are designed to ensure that all service providers established in the Member
States are treated on equal terms and that discrimination on the grounds of origin in a
particular Member State is avoided. The services listed in Part B of the relevant schedule
to the Services Directive are subject to lighter rules. They do not need, for example, to
be advertised in OJEC (35) but they should still
normally be acquired by competition to ensure best value for money.
4.10 Under these rules, the options for the
procurement procedure are:
Open procedure when all interested parties may bid.
Restricted procedure when only bidders who have pre-qualified at the
selection stage (see Chapter 5) are invited to bid. There must be
sufficient bidders to ensure genuine competition and no less than three, if available.
Negotiated procedure with a call for competition under which the terms of
the contracts may be negotiated with competitive potential providers. This procedure is
only permissible in defined circumstances that are set out in the rules. Subject to there
being sufficient suitable providers, no less than three must be invited. (This is the
accepted procedure for PFI procurements.)
Negotiated procedure without a call for competition In the very
exceptional circumstances set out in the rules, the negotiated procedure may be used
without a call for competition.
The accelerated procedure should only be used in exceptional circumstances and
where the Department is satisfied that its use can be fully justified.
4.11 Even if the contract is below the threshold
for EC Rules to apply, or in cases where the EC Procurement Rules do not require
competition, Departments must comply with EC Treaty obligations. In particular, they must
not discriminate against suppliers or contractors on the grounds of their nationality or
the Member State in which they are based.
Nature of the relationship
Partnering what is it?
4.12 Departments should decide before tendering
what sort of relationship is wanted with the service provider chosen through the
procurement strategy. It will depend on the extent to which strategic goals are shared. If
there is little, the contract will be at arm's length and the scope for better quality
services at optimal cost may be limited but these relationships are appropriate in
circumstances when the service is not critical to the Department's strategic objectives.
If there is a high degree of shared strategic goals, the relationship may be known as
"partnering" (36). The range of
possibilities between Departments and their service providers (37)
is illustrated in the table opposite:
This section is presented in Portable Document Format (PDF).
To read it you will first need to download the Adobe Acrobat Reader software. For more
information regarding PDF documents and how to load the software, please click here
The range of possibilities between Departments and their service
providers
How to approach partnering
4.13 Partnering arrangements are by no means soft
options. To optimise the benefits, they require significant resources of time and effort
during procurement as well as in managing the contract. There must be a competition at the
outset to select partners, run in accordance with the relevant EC Procurement Rules, where
they apply, and periodic competitions afterwards. There must be a contract defining the
responsibilities of both parties with measurable performance targets and milestones for
service improvement. Such contracts may well be longer than other contracts (see Chapter
8). In view of the nature of the relationship and the length of the contract, it will be
essential that partner selection is sound. Complementary cultures and attitudes based on
trust, mutual respect for objectives, flexibility and open communication will also be
critical to success.
Risks in partnering
4.14 There are also risks in partnering, which need
to be carefully considered:
 | strategic dependence, which might remove or reduce Departments' ability to seek
improvements in efficiency and quality by changing contractor; |
 | loss of the ability to take advantage of developments elsewhere in the public and
private sectors; |
 | unless specifications are comprehensive and tight, potential for the roles of purchaser
and provider to become blurred or reversed over time. |
Partnering, not legal partnership
4.15 Partnering should not imply a partnership in
law with a private company (under the Partnership Act 1890), which involves
responsibilities for each other's debts and which, therefore, the public sector cannot
enter, except through a special purpose company created for a joint venture.
ASSESSING FEASIBILITY
Purpose
4.16 Departments should establish whether or not
the recommendations made during scoping are feasible and, if so, how they will be
implemented. The feasibility study lays the foundations for competitive tendering and
provides an opportunity to:
 | confirm whether or not the recommendations made during scoping are sound; |
 | consider all those factors that are likely to have a bearing on implementation; |
 | confirm and develop the procurement strategy; |
 | produce an implementation plan. |
4.17 In confirming the recommendations made during
scoping, much of the same ground will need to be covered, but in greater depth and with
the practical issues associated with competitive tendering and managing the service to the
fore. When considering the requirements, there will be a need to understand the scope for
improvements, the risks associated with delivery and the current costs of provision. As in
scoping, the views of appropriate specialists, customers/end users and other stakeholders
should be sought.
Key issues to consider
4.18 Departments should consider all those issues
that are likely to have a bearing on competitive tendering and the viability of subsequent
contractual relationships, examples of which are given below.
 | Accountability providing clear lines of responsibility, so that the
requirements of Accounting Officer, and Ministerial, accountability can be met. |
 | Legal considering any legal restrictions and any impending legislation
that might affect implementation or constrain procurement. |
 | Financial considering the handling and management of public funds. |
 | Cashflow how will the likely pattern of payments or resource use fit with
the Department's resource balances. Will the cashflow requirements of the contract be
affordable? |
 | Timing and phasing how long will the competition take from start to
finish, that is from first review to contract. Will improvements and savings be delivered
in time to meet the Department's and its customers/users' needs for better quality and
cost effectiveness. |
 | Contractual considering aspects such as contract length, pricing
mechanisms, the treatment of assets, and contract management. |
 | Risks considering the risks involved in delivering the service/s in
question and whether or not adequate provisions, including insurance, could be made for
their management. |
 | Security considering requirements for protecting sensitive information and
assets and whether these might impact on procurement. |
 | Rights to intellectual property considering whether satisfactory
provisions could be made for handling any intellectual property on transferring work to
external contractors and in subsequent competitions. |
 | Human resources considering the effects on personnel management within the
area in question on issues such as whether or not TUPE will apply, the possible extent of
any redundancies, the need to retain an intelligent customer function or any local work
agreements. In addition, the implications for broader issues such as the retention of core
competencies, the effects on continuity and career structures and equal opportunities
should be considered. |
Consultation requirements
4.19 During feasibility studies, Departments should
seek the views of trade unions, where they are recognised, and other independent staff
representatives in other cases. There is a statutory requirement to provide them with a
copy of the procurement strategy that is to be followed and give an opportunity to
comment.
KEY MESSAGES
 | Scoping involves defining the boundaries of
the service required and bringing together packages of activities to maximise the benefits
of the efficiency exercise and minimise the process costs. |
 | Existing service providers, users and
potential providers should be consulted. |
 | The procurement strategy followed should
depend on the service being subjected to competition, its size and importance, and the
likely level of private sector interest. |
 | Partnering offers benefits if approached
with care and diligence it is not a soft option but there can be drawbacks
if the motivation of one party is dubious or if the parties do not respect each other's
objectives and aspirations. |
 | Assessing feasibility is important to
ensure that what was defined in scoping will work and in order to be clear about the
resource implications. |
|
SOURCES OF FURTHER
INFORMATION
 | Setting New Standards A Strategy
for Government Procurement Cm 2840 HMSO May 1995, ISBN 0-10-128402-0. |
 | Maximising Value from Public Sector
Assets: Selling Services into Wider Markets, HM Treasury. |
 | Competing for Quality Policy Review,
HMSO July 1996, ISBN 0-11-430142-5. |
 | CUP Guidance Note: No 40. |
 | CUP Guidance Note: No 51. |
 | CUP Guidance Note: No 57 Strategic
Partnering in Government, HM Treasury, Procurement Group. |
 | Towards Best Practice: An evaluation of
the first two years of the Public Sector Excellence Programme 1996-98, Cabinet Office,
1996. |
 | Partnerships for Prosperity: The Private
Finance Initiative, HM Treasury Taskforce, 1997. |
|
Footnotes
(21) See paragraph 3.13 et seq, below
(22) See paragraph 3.26 et seq, below
(23) The Government Actuary's Department (GAD) provides a helpful and substantial
checklist: GAD, or the Cabinet Office, Office of Public Service, Civil Service Pensions
Division, Basingstoke
(24) TUPE is to be amended following amendments to the acquired rights directive agreed in
June 1998. These changes will not reduce the scope of TUPE. There will be consultation, in
due course, on draft revised TUPE regulations.
(25) See paragraph 3.6, above
(26) See paragraph 3.9. above
(27) See Government Actuary's Department checklist on dealing with pension issues
available from GAD or the Cabinet Office, Office of public Service, Civil Service Pensions
Division, Basingstoke
(28) Civil Service Pension Division of the Cabinet Office, Office of Public Service,
Alencon Link, Basingstoke
(29) Guidance on Privatisation and Redundancy Guarantees - letter to Principal
Establishment and Finance Officers, HM Treasury, 2 March 1994
(30) See CUP Guidance Note 40
(31) See Maximising Value from Public Sector Assets: Selling Services into Wider Markets
(32) See Competing for the Quality Policy Review, 1996
(33) See Partnerships for Prosperity: the Private Finance Initiative, HM Treasury
Taskforce, 1997, for guidance on risk allocation in PFI deals
(34) See CUP Guidance Note 51
(35) Although, as good practice, they should still be advertised in Government
Opportunities - see Chapter 5
(36) See CUP Guidance Note 57
(37) There may also be similar, but separate partnering arrangements between service
providers, involving in-house teams and service providers from other Departments or the
private sector, or between service providers from other Departments and the private sector
(see Chapter 5)
(38) Partnerships for Prosperity: the private Finance Initiative, HM Treasury Taskforce,
1997
|

|